Kit list — BOM rev C × 30Issued from stock
| Part | Bin | Per unit | Needed | On hand | |
|---|---|---|---|---|---|
| M-BOB39 Bobbin ETD39 20-pin | C1-05 | 1 ea | 30 | 61 | Issued |
| M-ETD39 Ferrite core pair ETD39 N87 | C1-02 | 1 ea | 30 | 130 | Issued |
| M-LITZ100 Litz wire 100 × 0.1mm | C2-02 | 3.5 m | 105 | 168 | Issued |
| M-TAPE Polyester insulation tape 25mm | C2-03 | 1.5 m | 45 | 337 | Issued |
| M-WIRE08 Enamelled copper wire 0.8mm | C2-01 | 12 m | 360 | 1,032 | Issued |
Serials & test records (0)
Sub-assemblies are booked into stock without serials.
Works order
- Builds
- MAG-T240
- Quantity
- 30 · 30 built
- Stage
- Complete
- For
- Stock build
- Released
- 23 Oct 2026
- Due
- 06 Nov 2026
- Completed
- 02 Nov 2026
- Assigned
- Grace O'Brien
- Build time
- 17.5 h (35 min each)
- Std cost
- $55.71 each · $1,671.30
Build for stock — reorder point
Build documentsAll →
BOM-MAG-T240
Bill of materials
C Released