KaRaTec
KA
WO-26-1346
MAG-T360 ×24 — Main transformer 360W, ETD49
MYOB · synced 08:55
Demo
03 Nov 2026
⌘K
4
Take the tour
Planned
Kitted
PCB assembly
Final assembly
Burn-in & test
QC & pack
Complete
Rev D
Late — due 01 Nov 2026
Move to Final assembly
Edit
Traveller
Kit list — BOM rev D × 24
Issued from stock
Part
Bin
Per unit
Needed
On hand
M-BOB49
Bobbin ETD49 20-pin
C1-06
1 ea
24
136
Issued
M-ETD49
Ferrite core pair ETD49 N87
C1-03
1 ea
24
136
Issued
M-LITZ100
Litz wire 100 × 0.1mm
C2-02
5 m
120
168
Issued
M-TAPE
Polyester insulation tape 25mm
C2-03
2 m
48
337
Issued
M-WIRE08
Enamelled copper wire 0.8mm
C2-01
14 m
336
1,032
Issued
Serials & test records (0)
Sub-assemblies are booked into stock without serials.
Works order
Builds
MAG-T360
Quantity
24
Stage
PCB assembly
For
Stock build
Released
23 Oct 2026
Due
01 Nov 2026
Assigned
Grace O'Brien
Build time
18 h (45 min each)
Std cost
$73.58 each · $1,765.92
Build for stock — reorder point
Build documents
All →
BOM-MAG-T360
Bill of materials
D
Released
KA
Karna
karna@karatec.com.au
My profile
Account settings
Emails sent
Take the guided tour
Show screen tips again
View as
Karna — General Manager
Daniel Okafor — Engineering Manager
Priya Raman — Electronics Design Engineer
Tom Barker — Test & Compliance Engineer
Mei Lin — Sales & Customer Service
Sarah Whitfield — Accounts & Administration
Andrew Costa — Production Supervisor
Linh Nguyen — PCB Assembly Technician
Hassan Ali — Assembly Technician
Grace O'Brien — Coil Winding & Assembly
Josh Mitchell — Test & QC Technician
Ben Taylor — Stores, Purchasing & Dispatch
▤