Kit list — BOM rev C × 34Issued from stock
| Part | Bin | Per unit | Needed | On hand | |
|---|---|---|---|---|---|
| ENC-GBX sub-assy Enclosure kit, GBX | K5-03 | 1 ea | 34 | 77 | Issued |
| PSA-GBX60 sub-assy Power stage PCBA, GBX 60W | K2-09 | 1 ea | 34 | 34 | Issued |
| J-PC5-2 Terminal block 2-pos 5.08mm | D2-01 | 2 ea | 68 | 311 | Issued |
| P-CTN-S Carton small, printed | H1-01 | 1 ea | 34 | 280 | Issued |
| P-GUIDE Installation guide, printed | H1-05 | 1 ea | 34 | 247 | Issued |
Serials & test records (34)All →
First unit KT26-15040 · tested by Josh Mitchell on 24 Aug 2026
Input
48 VDC
Output @ 100%
23.98 V
Efficiency
89.6%
Ripple
46 mV
Burn-in
24 h
Result
Pass
| Serial | Rev | Vout | Eff. | Ripple | Result | Status |
|---|---|---|---|---|---|---|
| KT26-15040 | C | 23.98 V | 89.6% | 46 mV | Pass | Shipped |
| KT26-15041 | C | 23.99 V | 89.5% | 31 mV | Pass | Shipped |
| KT26-15042 | C | 23.97 V | 89.6% | 23 mV | Pass | Shipped |
| KT26-15043 | C | 24.01 V | 89.3% | 29 mV | Pass | Shipped |
| KT26-15044 | C | 23.96 V | 88.5% | 42 mV | Pass | Shipped |
| KT26-15045 | C | 24.02 V | 89.3% | 35 mV | Pass | Shipped |
| KT26-15046 | C | 23.99 V | 88.6% | 24 mV | Repaired | Shipped |
| KT26-15047 | C | 24.00 V | 87.1% | 30 mV | Repaired | Shipped |
| KT26-15048 | C | 23.99 V | 89.7% | 62 mV | Pass | Shipped |
| KT26-15049 | C | 24.01 V | 88.2% | 34 mV | Pass | Shipped |
| KT26-15050 | C | 23.98 V | 87.8% | 20 mV | Repaired | Shipped |
| KT26-15051 | C | 23.96 V | 89.7% | 30 mV | Pass | Shipped |
| KT26-15052 | C | 24.01 V | 88.5% | 60 mV | Pass | Shipped |
| KT26-15053 | C | 23.99 V | 88.7% | 45 mV | Pass | Shipped |
| KT26-15054 | C | 24.03 V | 87.4% | 35 mV | Pass | Shipped |
| KT26-15055 | C | 24.01 V | 89.8% | 56 mV | Pass | Shipped |
| KT26-15056 | C | 23.97 V | 89.6% | 31 mV | Pass | Shipped |
| KT26-15057 | C | 24.02 V | 89.3% | 44 mV | Pass | Shipped |
| KT26-15058 | C | 23.97 V | 87.8% | 22 mV | Pass | Shipped |
| KT26-15059 | C | 24.03 V | 88.8% | 22 mV | Pass | Shipped |
| KT26-15060 | C | 23.97 V | 89.8% | 25 mV | Pass | Shipped |
| KT26-15061 | C | 24.02 V | 88.4% | 47 mV | Pass | Shipped |
| KT26-15062 | C | 24.02 V | 89.4% | 37 mV | Pass | Shipped |
| KT26-15063 | C | 23.99 V | 87.7% | 55 mV | Pass | Shipped |
| KT26-15064 | C | 24.04 V | 89.3% | 56 mV | Pass | Shipped |
| KT26-15065 | C | 23.99 V | 87.1% | 62 mV | Pass | Shipped |
| KT26-15066 | C | 24.01 V | 87.1% | 23 mV | Pass | Shipped |
| KT26-15067 | C | 24.00 V | 87.4% | 34 mV | Pass | Shipped |
| KT26-15068 | C | 24.04 V | 88% | 62 mV | Pass | Shipped |
| KT26-15069 | C | 23.97 V | 87.9% | 29 mV | Pass | Shipped |
| KT26-15070 | C | 23.95 V | 89.1% | 23 mV | Pass | Shipped |
| KT26-15071 | C | 24.00 V | 89.6% | 60 mV | Pass | Shipped |
| KT26-15072 | C | 24.01 V | 89.2% | 50 mV | Pass | Shipped |
| KT26-15073 | C | 24.02 V | 87.4% | 34 mV | Pass | Shipped |
Works order
- Builds
- GBX60-48-24
- Quantity
- 34 · 34 built
- Stage
- Complete
- For
- SO-26-0273Lumen Marine Systems
- Released
- 27 Jul 2026
- Due
- 31 Aug 2026
- Completed
- 24 Aug 2026
- Assigned
- Linh Nguyen
- Build time
- 8.5 h (15 min each)
- Std cost
- $111.49 each · $3,790.66
Build documentsAll →
DWG-GBX60-48-24
Assembly drawing
C ReleasedBOM-GBX60-48-24
Bill of materials
C ReleasedTP-GBX60-48-24
Test procedure
B Released